Saturday, June 9th, 2007

I got the rudder fully rigged. It is nice to be able to sit in the seat and actually push on the brakes and operate the rudder. I think this is the first time that I’ve gotten a good idea what the pedals are really going to feel like. I used a zip tie on each rudder linkage at the pedals to determine link length. Worked great.
Stu and Deene were replacing all four cylinders on Stu’s RV8 with new ECI cylinder assemblies in Stu’s hangar a few feet away. I ducked over there for a little while to soak up some top end overhaul wisdom. I learn cool new things every day that I’m out there just by being there. That is the whole goal of this project for me. Many thanks to those that are willing and able to share knowledge.

It was another one of those long days at the hangar that didn’t quite produce the results that one would expect, but it all has to get done somehow. Tanya brought lunch and headed for home around 5pm. She spent most of her time picking up the tool mess that I had made the previous week. She only comes out on the weekend while I’m out there every day. I warned her that I had almost emptied all of the tool chests onto the work benches :).

After the rudder was all squared away, I took care of other little stuff. I got a connector shell on the autopilot roll servo wiring and secured the wires. I installed the seat rib cutouts, and gapped and installed a new spark plug for one that I had dropped.

I do now have a “short list” that I’m beginning to consult.

 
  
  
 

Rudder installed

Thursday, June 7th, 2007

I finished up installing the elevator trim servo. I wired it with molex micro-fit 3.0 pins with no connector shell. I left a little service loop with the connectors on it coiled above the servo in the elevator. Everything all neatly heat shrinked together. Elevator removal should entail removing the servo, cutting off the outer shrink tube and the shrink tube on each of the five connectors. Then the wire will be pulled through a snap bushing in the elevator spar. The wire will then need to be fished back through upon reassembly.

Moving on to the rudder. I double checked the hinge rod end bearing alignment and secured the rod end jam nuts on the rudder spar with some loctite. I dressed the rudder wires through a snap bushing and through some expandable wire sleeve for protection. It was very easy to fish the wires up through the permanently secured rudder bottom. I installed the requisite connectors and then it was time for a light show!

Now, for the first time, I have all three nav lights and all three strobe lights all wired up. Lets see if we can keep the blue smoke from getting out :). I put fuses in those two circuits. At about this time, Jim showed up from his hangar after having a little bit of a frustrating evening with aileron assembly. He already had a beer in hand, so I had an audience just in case anything went terribly wrong with the first test of these two circuits. I threw the nav light switch and they all came on just they are supposed to. Cool. Now for the real exciting part, I flipped on the strobe switch and we had a full on light show in the hangar. All the strobes came up and fired in the correct pattern. Those things are bright. Amazing, all that circuitry and everything worked just right the first time.

So, now all the big parts are on the airframe. I still need to rig the rudder controls but it looks like a complete airplane.

 
  
  
  
  
 

Elevators

Tuesday, June 5th, 2007

I started rigging the elevators. I got the hinge rod end bearings adjusted and secured and the hinge bolts torqued. The center pivot bolt went in without a problem, and I used my standard washer insertion trick of using a piece of scotch tape (actually the 3M rivet tape that I used) to put a little “handle” on the washers to put them in place while pushing the bolt through. Piece of cake. I worked out the push tube length and I’m very happy with it.

 
  
 

Update: Empennage done / Preparing for wings

Saturday, February 26th, 2005

I have cleaned up after finishing the empennage fiberglass tips. I’m not currently planning on doing full blended and filled tips like some people do. I reserve the right to change my mind later, but as it sits, all of the tips have been trimmed, fitted, filled, adjusted, etc. All of the empennage components have been put away for extended storage while the wings and fuselage are constructed. We have fully cleaned up the garage in preparation for the wing kit, due to ship in the next week.

Tomorrow I’m going to get things together to construct the wing jig. I’m planning on building both wings at the same time, so I’ll really be building two wing jigs about three feet apart (maybe a little more, depending on what the space looks like).

Trimming fiberglass tips

Thursday, February 3rd, 2005

The past few days I’ve been spending just a few minutes each evening trimming the fiberglass tips just to keep myself busy. This evening I jigged up the rudder (top) tip and left it in front of the space heater to do some minor reshaping for a better fit. We’ll hopefully see positive results tomorrow after it cools.
Just burning time until the wing kit gets here.